TECHNICAL PROCESSING AND INSTALLATION OF REINFORCED STEEL

News
Date Submitted: 05/09/2024 09:37 AM

TECHNICAL PROCESSING AND INSTALLATION OF REINFORCED STEEL

The processing and erection of reinforcement is in accordance with the detailed steel design of the structure and the general regulations of the design documents of the construction project. What are the technical requirements for processing and erecting rebar? How is it done? Join Hung Nghiep Phu to find answers through the updated information below!

    1. Type of steel

    Steel is an important material in construction. The physical and mechanical criteria (steel grade) are in accordance with the design regulations and the type is in accordance with the contract (if any) previously given.

    • When steel is imported to the project, the engineer, along with the supervision consultant and the investor, check the quality certificate of the steel batch and prepare a material acceptance record.
    • Based on the quantity and type, cut steel samples in accordance with TCVN 197: 1985 standards to conduct experiments on physical and mechanical properties of steel. After cutting the steel sample, the parties will prepare a sampling record and seal the steel sample and transfer it to the testing unit.
    • The testing unit is an independent consulting unit submitted by the construction unit and approved by the supervisor. When conducting experiments, there must be full monitoring by all parties.
    • Based on the test results, it is determined whether the batch of steel imported to the project can be used for the project or not, and is also the basis for finalizing the contract to supply steel materials.

    2. Cleaning and polishing steel

    Before being put into construction, steel construction must go through cleaning and rusting. If the steel is rusty or covered in mud, then install it into the structure.

    Steel must be cleaned of mud and rust (if any) before being processed or installed into the structure. Rusty steel is steel that has had steel scales, peeling off the outer layer. If the steel is just yellow, there is no need to clean the steel. If the rust layer reduces the steel cross-section by more than 2%, this type of steel is considered "damaged" and cannot be used. Otherwise, the quality and safety of the project will not be guaranteed.

    • Brush the rust with a wire brush or machine.
    • Treat rust with chemicals.
    • If dirty, you can wash it with a sprayer or wipe it with a wet cloth.

    3. Processing rebar 

    • Reinforcement processing requirements are in accordance with the detailed steel design of the structure and the general regulations of the previously agreed upon design documents.
    • Carefully read detailed steel drawings of structures on plans, sections, architectural drawings...
    • Deploy detailed steel processing designs and supervise for approval. Steel details must comply with the steel connection position. 
    • During the steel processing process, supervision of both parties is required.

    4. Erecting reinforcement

    Reinforcement erection techniques require the right location, the right elevation, and every inch of precision. 

    • For foundations, beams, floors, and stairs, follow the pre-fabricated and installed floor beam beam positioning system;
    • For columns and walls, from the deployed grid on the deployment floor, turn on the column and wall foot sections and adjust the steel, wait to ensure the protection layer before proceeding with steel erection.
    • The protective layer complies with the design regulations for each component.
    • The main steel frame must be stable and have the correct structural shape.
    • The construction steel belt must be straight and evenly spaced by first determining the belt and then using a ruler or measuring stick and marking with chalk on the main steel for workers to tie the belt. The steel straps must be arranged alternately with cross-hook points.

    Gia công lắp dựng, cốt thép

    5. Joining steel in rebar erection work

    Connect at the correct location (compression area), at the correct length and in accordance with general design regulations.

    • For floor beams if not specifically specified; Normally, the connection location must not be in the danger zone. One section must not connect more than 50% of the steel.
    • Connection length according to design regulations; If there is no special regulation, the connecting section is 30d in the compression zone; 40d in tow zone (limited use).
    • At the steel connection position, if the bearing steel has a diameter >= 18; the steel must be bent at the connection position so that 2 steel bars; After connecting, it must be concentric (press the neck of the bottle).

    6. Steel bars create a protective concrete layer

    Sufficient strength (if using concrete or high-grade mortar); and ensure the thickness of the protective layer.

    • Steel supports must be cast first to ensure that they will not break when being constructed.
    • At one location, two beams must be placed so that the frame is not twisted and is stable.
    • Dog legs placed on top of the steel layer of the floor: If not specifically specified, dog legs; usually made of steel with a diameter of 10 or 12. In addition, depending on the situation, determine the appropriate type of steel.

    7. The process of pouring concrete and erecting steel reinforcement.

    During the pouring of concrete; A steel reinforcement team must be arranged to repair warped areas. Use hooks to repair the steel floor.

    8. Introducing a reputable design & construction consulting service provider

    The importance of construction units is undeniable because their reputation will ensure the quality and aesthetics of your project. Today, there are many units providing construction design services to meet the increasing construction demand in our country. Therefore, finding a reputable unit is not easy and requires you to spend time researching. During the selection process, you need to research carefully and ensure that the accompanying unit must have high professional qualifications, many years of experience, have a clearly signed contract, transparent costs,... To Helps customers save time searching, Công ty TNHH Đầu tư Xây dựng Hưng Nghiệp Phú confident that it will be the best choice for you.

    Giày Sneaker en

    Hung Nghiep Phu Construction Investment Co., Ltd. with the mission of bringing the best solutions and services, building a prosperous community with customers, Hung Nghiep Phu is gradually asserting its brand through cooperation. Sincere cooperation, with a leadership team with ethical capacity, creativity, dedication to the profession and strategic vision. Hung Nghiep Phu owns a team of skilled and highly qualified staff who will bring customers the best quality projects. 

    Hung Nghiep Phu Construction Investment Company Limited - specializes in constructing civil and industrial projects. We look forward to accompanying customers in construction projects as well as legal procedures such as planning diagrams, applying for construction permits, completing procedures, and applying for fire prevention and fighting certificates. ,... If you have any questions or are in need of designing and completing procedures, please contact us immediately for a free consultation!

    >>> See more:

    _____________________

    THÔNG TIN LIÊN HỆ:

    ???? Facebook: Công ty TNHH Đầu tư Xây dựng Hưng Nghiệp Phú (興業富) 

    ☎️ Đường dây nóng: 1800.3368 (Miễn phí)

    ???? Trang web: xaydunghunnghiepphu.com

    ???? Gmail: kinhdoanh01@xaydunghungnghiepphu.com

    ???? Address: No. 2034D, group 22, KP. Phuoc Thai, Thai Hoa Ward, City Tan Uyen, Binh Duong Province

    ------

    Source: Collected Internet